UV Sterilizer Installation Acceptance Standards and Test Methods

Installation acceptance is the final checkpoint before a UV sterilizer is put into service; the unit may only enter operation once acceptance has been passed. Longkang has established a complete set of installation acceptance standards to ensure installation quality and operating performance. This article explains the acceptance criteria and test methods in detail.
1. Acceptance Basis
- GB/T 19837 — Ultraviolet Disinfection Equipment for Municipal Water Supply and Drainage
- GB 50242 — Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Works
- GB 50303 — Code for Acceptance of Construction Quality of Building Electrical Engineering
- CJJ 140 — Technical Code for Secondary Water Supply Engineering
- CJJ 110 — Technical Code for Pipeline Direct Drinking Water Systems
- Product manual and installation drawings
- Technical requirements specified in the contract
2. Acceptance Procedure
- The installation contractor completes and passes its self-inspection
- Submit the acceptance application and documentation
- The project owner / supervision consultant organises the acceptance
- On-site inspection and testing
- Complete the acceptance records
- Sign off once acceptance is passed
- Hand over the documentation
- Put the unit into operation
3. Visual Acceptance
3.1 Equipment Appearance
- Surface is clean and smooth, with no scratches, dents or deformation
- Welds are even, with no porosity or cracks
- Outer coating is uniform, with no peeling
- Nameplate is firmly mounted and the information is legible
- Warning labels are complete
- Unit is clean and free of oil stains
3.2 Installation Appearance
- Unit installed in the correct position
- Unit is level (checked with a spirit level)
- Unit is firmly fixed with no looseness
- Foundation or support is solid
- Surroundings are tidy and free of debris
- Adequate maintenance clearance (≥0.5 m)
3.3 Pipework Appearance
- Pipework is laid out logically, horizontal and vertical where required
- Pipe connections are correct and free of leakage
- Pipe supports are firm and independent
- Valves are correctly installed and operate freely
- The strainer is correctly installed
- The bypass line is correctly installed
- Pipe markings are clear (flow direction)
3.4 Electrical Appearance
- Control cabinet is firmly mounted
- Door opens freely and seals well
- Cables are neatly routed and protected by conduit
- Cable entries are sealed against water ingress
- Wiring is neat and wire numbers are clear
- Labels are legible
- Grounding is reliable
4. Dimensional Acceptance
4.1 Equipment Dimensions
- Overall dimensions: comply with the drawings, tolerance ±5 mm
- Installation dimensions: comply with the drawings, tolerance ±2 mm
- Connection dimensions: comply with the standard
- Centre height: complies with the design
4.2 Installation Clearance Dimensions
- Distance to wall: ≥0.5 m
- Distance to other equipment: ≥0.5 m
- Headroom above the unit: ≥0.3 m (for lamp replacement)
- Operating-face clearance: ≥0.8 m
4.3 Pipework Dimensions
- Pipe diameter: complies with the design
- Slope: ≥0.003 (where required)
- Pipe coaxiality: ≤2 mm
5. Pipework System Acceptance
5.1 Connection Inspection
- Flanged connections: bolts complete, tightened diagonally, gaskets correct
- Threaded connections: PTFE thread seal tape correctly applied, no leakage
- Welded connections: weld quality acceptable, free of defects
- All connections free of leakage
5.2 Valve Inspection
- Valve models are correct
- Valves open and close freely
- No internal leakage (no water passes when closed)
- Valve markings are clear (normally open / normally closed)
5.3 Strainer Inspection
- Strainer model is correct
- Filter screen is intact
- Installation direction is correct
- Drain valve functions normally
5.4 Bypass Inspection
- Bypass line is unobstructed
- Bypass valve opens and closes freely
- The unit can be isolated when the bypass is in use
5.5 Hydrostatic Pressure Test
- System hydrostatic test: 1.5 times the working pressure
- Hold pressure for 30 minutes
- No leakage and no pressure drop
- Keep a test record
6. Electrical System Acceptance
6.1 Power Supply Inspection
- Voltage: 220 V ±10% or 380 V ±10%
- Frequency: 50/60 Hz
- Circuit breaker rating is correct
- Residual-current protection operates normally (trips at 30 mA)
- Power supply capacity is adequate
6.2 Wiring Inspection
- Wiring is correct (checked against the wiring diagram)
- Live, neutral and earth conductors are correctly connected
- Connections are firm with no looseness
- Wire numbers are clear
- No exposed conductor ends
6.3 Insulation Resistance Test
- Insulation resistance: ≥2 MΩ (500 V megohmmeter)
- Test points: live-to-enclosure, neutral-to-enclosure, live-to-neutral
- Record the measured values
6.4 Grounding Test
- Grounding continuity: ≤0.1 Ω
- Grounding resistance: ≤4 Ω
- Earth conductor not smaller than the power conductor
- Earth conductor in yellow/green bicolour
6.5 Dielectric Strength Test
- 1500 VAC for 1 min
- No breakdown and no flashover
- (If site conditions do not permit, refer to the factory test report)
7. Operating Performance Acceptance
7.1 Start-Up Test
- Switch on power; lamps start normally
- Start-up time <1 s (low-pressure lamps)
- All lamps are lit
- No flicker and no abnormality
7.2 Continuous Operation
- Continuous operation for 2 hours
- Lamp output remains stable
- Operation indicator is lit
- No abnormal noise or odour
- No tripping and no alarms
- Ballast temperature ≤70°C
7.3 Parameter Measurement
- Inlet pressure: 0.1–0.6 MPa
- Outlet pressure: no more than 0.05 MPa below the inlet pressure
- Flow rate: reaches the rated flow
- UV intensity: ≥ design value (with new lamps)
- Input voltage and current: normal
- Power factor: ≥0.95
7.4 Protection Function Test
- Overcurrent protection: simulate an overcurrent, protection operates
- Short-circuit protection: simulate a short circuit, protection operates
- Alarm function: simulate a fault, alarm operates
- Elapsed-time counter: lamp operating hours accumulate normally
- Remote communication (if fitted): communication is normal
7.5 Interlock Test
- Interlock with the water pump: pump starts, then the sterilizer starts
- Interlock with the tank water level
- Standby changeover (if fitted): duty-unit fault, then the standby starts
- Remote start / stop (if fitted)
8. Disinfection Performance Acceptance
8.1 Water Quality Testing
- Inlet water quality testing
- Outlet water quality testing
- Test items:
- Total bacterial count: ≤100 CFU/mL (for drinking water)
- Total coliforms: not detectable
- Faecal coliforms: not detectable
- Pathogenic bacteria: not detectable
- Complies with GB 5749 — Standards for Drinking Water Quality
8.2 Inactivation Rate Calculation
- Inactivation rate = (inlet count − outlet count) / inlet count × 100%
- Inactivation rate ≥99.99% (at 40 mJ/cm²)
- Or ≥99.999% (at 60 mJ/cm², for direct drinking water)
8.3 UV Dose Verification
- Readings from the UV intensity monitor
- Calculated from flow rate × exposure time
- Or third-party biodosimetry testing
- Dose ≥ design value
8.4 Third-Party Testing (Where Required)
- A qualified third-party testing organisation
- On-site sampling and testing
- Issue a test report
- Serves as an acceptance basis
9. Documentation Acceptance
9.1 Product Documentation
- Product certificate of conformity
- Product manual
- Electrical schematic and wiring diagrams
- Installation drawings
- Hygiene permit for water-contact products (copy)
- Factory test report
- Third-party disinfection efficacy test report (copy)
9.2 Installation Documentation
- Installation records
- Concealed-work acceptance records
- Pipe hydrostatic test records
- Electrical insulation test records
- Grounding test records
9.3 Commissioning Documentation
- Commissioning records
- Operating parameter records
- Water quality test report
- Interlock test records
9.4 Acceptance Documentation
- Acceptance application
- Acceptance records
- Acceptance report
- Handover list
- Warranty card
10. Summary of Acceptance Criteria
| Acceptance item | Criterion | Verification method |
|---|---|---|
| Appearance | Clean and free of defects | Visual inspection |
| Levelness | ≤2 mm/m | Spirit level |
| Pipe leakage | No leakage | Visual inspection, hydrostatic test |
| Hydrostatic test | 1.5 times pressure, no leakage for 30 min | Pressure test pump |
| Insulation resistance | ≥2 MΩ | Megohmmeter |
| Grounding resistance | ≤4 Ω | Earth resistance tester |
| Lamp ignition | All lamps lit | Visual inspection |
| Continuous operation | 2 h with no abnormality | Running test |
| UV intensity | ≥ design value | UV intensity meter |
| Head loss | ≤0.05 MPa | Pressure gauge |
| Outlet water quality | Complies with GB 5749 | Water quality testing |
| Inactivation rate | ≥99.99% | Calculation |
| Documentation | Complete | Document review |
11. Handling of Nonconformities
- Minor nonconformity: rectify within a set period, then re-inspect
- Major nonconformity: suspend work for rectification, then repeat the full acceptance
- Nonconformity records: record the nonconforming items, corrective actions and re-inspection results
- Once all items pass: sign the acceptance report and put the unit into operation
12. Longkang Acceptance Services
- Provide detailed acceptance standards and checklists
- Post-installation self-inspection to ensure compliance
- Cooperate with the project owner / supervision consultant during acceptance
- Provide all acceptance documentation
- Support for water quality testing
- Prompt rectification of acceptance issues
- Operator training after acceptance
- Lifetime technical support