UV System Troubleshooting: A Field Checklist

Where lamp diagnosis looks at the tube, this checklist looks at the whole reactor. Most callouts trace back to three symptoms — and most of those trace back to installation, not hardware.
Symptom-to-cause table
| Symptom | Likely cause | Action |
|---|---|---|
| Water at the sleeve end | Cracked quartz; gland not torqued; failed O-ring | Replace sleeve, tighten evenly (do not over-torque), renew seal |
| Low log reduction | Supply voltage low; sleeve fouled; lamp output below 70 µW/cm²; lamp past rated hours; flow above rating; turbidity or suspended solids high | Correct voltage; clean sleeve; replace lamp; check flow; add pre-filtration |
| Lamp will not strike | Blown fuse; loose socket; broken socket tab; failed ballast; failed indicator; damaged lamp | Work from supply to lamp, replacing only what tests bad |
Installation details that prevent the callout
- Vertical mounting: feed low, discharge high, so the chamber stays full and flow slows through the irradiation zone.
- High flow velocity: fit a flow or pressure limiter. Water that rushes past the sleeve does not collect dose.
- Pressure above 3 kgf/cm²: fit a check valve on the outlet to protect the quartz sleeve.
- Solenoid valve: put it on the inlet, upstream of the reactor.
- Turbidity above 5 NTU: pre-filter. Particles shield organisms.
- Service clearance: leave more than 1.2 m at one end for lamp withdrawal and a drain nearby.
Do not skip the safety steps
Never look at a lit lamp directly. Isolate power before opening the chamber, wear UV-rated eye protection and gloves, and let the lamp stabilise for five to ten minutes after striking before judging output. Quartz should be handled with a clean cloth — fingerprints carbonise under UV-C and permanently cut transmission.
One habit pays for itself: log lamp hours, intensity reading and sleeve condition at every visit. A trend tells you whether you are looking at consumable ageing or a design mismatch. Swapping a lamp without logging anything just resets the clock on the same problem.