Flowchart Analysis for WWTP Process Management

In wastewater treatment plants, since total nitrogen and total phosphorus came under monitoring, plant management has improved considerably. Ammonia nitrogen exceedance, once a troublesome issue, is no longer considered a difficult problem: virtually every plant now has a solution in place and has continuously refined its process response through practice. Because effective solutions for ammonia nitrogen exceedance already exist at most plants, and operators have accumulated substantial field experience, this article presents a typical troubleshooting workflow for ammonia nitrogen exceedance, so that process operators can integrate it into their own plants’ response plans and use it to analyze and manage process operation.
Why a troubleshooting flowchart
When an ammonia nitrogen exceedance occurs, many site problems need to be resolved at once, and the situation is often chaotic. Field operators need clear process guidance, yet complete and accurate operating data for analysis is often not available. This is precisely why an analytical decision flowchart should be prepared for operators: it guides them step by step through the analysis and adjustment of the ammonia nitrogen problem until the issue is resolved. The flowchart presented here works through a sequence of “yes” and “no” answers that direct the operator to the next process action.
The greatest advantage of this kind of decision flowchart is that every level involves only a simple yes-or-no answer, so operators can quickly work through the analysis until they find the root cause. Each decision node in the flowchart is accompanied by detailed notes and explanations, compiled into a companion reference manual attached to the flowchart, so that operators can read and study it until they fully master and apply it.
That said, conditions vary greatly from plant to plant. This flowchart is presented as one example of ammonia nitrogen exceedance analysis, not as a standard procedure to be promoted universally. Interested readers are encouraged to adapt it to the realities of their own plants and develop a set of process anomaly detection workflows suited to their own operation, enabling better on-site process management.
How to read the flowchart
This is a decision flowchart for ammonia nitrogen exceedance, in which each box represents one inspection item. Starting from the moment an ammonia nitrogen exceedance is reported, the process inspection begins at the yellow inspection box. Because conventional advanced treatment steps (chemical dosing, coagulation-sedimentation, filtration) generally only affect SS and total phosphorus, the inspection starts at the secondary clarifier effluent ammonia nitrogen. From that point, answer the question in each inspection box: a “yes” answer follows the green arrow to the next box, a “no” answer follows the red arrow. Each box references supporting material, organized into a series of “Quick Reference” notes so that the analysis can proceed step by step. Each Quick Reference item is followed by related extended content — mainly explanations of basic wastewater plant skills — making this series also an introduction to process management for wastewater plants.
Below is Quick Reference 1 for flowchart box one:
Quick Reference 1: Secondary clarifier effluent ammonia nitrogen below 5 mg/L
The criterion is that ammonia nitrogen in the secondary clarifier effluent is <5 mg/L. Pollutants in wastewater include carbonaceous organic matter (COD/BOD) and nitrogenous pollutants in the form of ammonia nitrogen (NH3-N). In the aeration tank, bacteria convert these pollutants in two ways: assimilation into new bacterial cell material for their own reproduction, and oxidation into CO² and nitrate (NO3-), preventing pollutants entering the plant from being discharged into natural water bodies. Nitrifying bacteria in the aeration tank convert the incoming ammonia nitrogen into nitrate (NO3-). These nitrifying bacteria are extremely sensitive to their growing environment. Because of this sensitivity, monitoring ammonia conversion within the plant provides an “early warning” indicator for nitrogen removal, telling the operator when process adjustments are needed. Changes in the various environmental conditions in the plant can limit the nitrifying bacteria’s conversion of ammonia to nitrate, ultimately increasing the ammonia nitrogen concentration in the aeration tank effluent — a sign that nitrification in the aeration tank is inhibited, leading to ammonia nitrogen exceedance in the secondary clarifier. If the ammonia nitrogen concentration in the aeration tank effluent is <5 mg/L, both major pollutant groups (COD/BOD and NH3) are considered successfully converted, so when the aeration tank effluent meets the target, the secondary clarifier effluent also meets it — that is, ammonia nitrogen <5 mg/L.
From this analysis it follows that biological nitrification in the aeration tank must be completed first. From an operational standpoint, the aeration tank effluent is always the first item to be checked in activated sludge system troubleshooting. If the ammonia nitrogen concentration in the secondary clarifier effluent exceeds 5 mg/L, this indicates that nitrification in the aeration tank is incomplete, or that ammonia is being released from activated sludge decomposition in the secondary clarifier. The key point to remember in box one: ammonia nitrogen is converted to nitrate only in the aerobic environment of the aeration tank.
Contact Longkang for operational support and process consultation.