UV Sterilizer Cleaning and Maintenance Steps

Wastewater UV sterilizer cleaning and maintenance steps
Quartz sleeve, cleaning system and cabinet maintenance.

The performance of a wastewater UV sterilizer mainly depends on whether the bacteria and viruses in the water receive an acceptable UV dose. Once the dose is sufficient, the UV light energy destroys the DNA structure of bacteria, viruses and other pathogens in the water, inactivating them and killing them off, so the water is disinfected and purified.

1. Cleaning the glass sleeve surfaces

To guarantee disinfection performance, the glass sleeves of the lamp racks must be cleaned manually at regular intervals.

  1. Wearing rubber gloves, wipe the glass sleeve surfaces with a cloth.
  2. After removing the dirt from the sleeve surfaces, rinse them with clean water.
  3. Unplug the rack’s heavy-duty connector, pack it in a clean bag, then lift the rack with a crane and place it on the maintenance trolley.
  4. Clear away any debris hanging on the rack.
  5. Spray a cleaning agent (weak acid or a commercial glass cleaner) onto the glass sleeve surfaces.
  6. When cleaning is complete, use the crane to lower the rack back into the installation frame and reconnect the heavy-duty connector.

2. Cleaning system maintenance

  1. The water-mist separator is mainly the manual-drain type. When the water level in the filter cup reaches one third of its height, rotate the knob at the bottom of the cup to drain it by hand and maintain mist-separation performance.
  2. Regularly check that the pressure of the filter-pressure-reducing valve meets the specified value, and observe the water accumulated in the filter cup. When the accumulation reaches a certain volume, the filter-reducing valve drains automatically, keeping the system running normally.
  3. Before use, check that the oil level inside the tank stays within the specified range; if it is low, top up to the proper level.
  4. Once a week, open the drain valve of the air storage tank to remove accumulated water.
  5. Regularly check all air piping for leaks.
  6. Regularly clean the cylinder tie rods to keep the rack travel smooth; the rack must not stick or jam during cleaning.

3. Ballast box and central control cabinet maintenance

  1. Check the operation of the air conditioner in the ballast box every day and ensure its cooling effect.
  2. Regularly remove dust from the surface of the electrical control cabinet.
  3. Check ballast operation every day and make sure every ballast works normally.
  4. Record every monitored value on the HMI of the central control cabinet daily, including current, voltage, lamp status, cabinet temperature, UV intensity and the status of the automatic cleaning system.
  5. Regularly check whether any wiring inside the cabinet has aged or come loose.

4. Water level control device maintenance

  1. Once a fixed overflow weir is installed, clean it regularly.
  2. With a flap-gate overflow weir, adjust the water in the channel according to flow variations so the water covers the first lamp and is kept within 6 cm above it.
  3. Regularly check the fixing screws of the flap-gate weir for looseness.
  4. An electric weir gate adjusts the water level automatically with flow variations. Its maintenance covers: (a) grease the motor and bearings regularly and check the motor wiring for looseness; (b) remove dust from the motor regularly and protect it from moisture and rain.

Contact Longkang for sizing support and quotations.

UV disinfection, storage tank treatment, on-site hypochlorite (OSHG), chlorine dioxide and ozone systems for municipal, high-rise booster and industrial water.

Contact

Hotline +86 4008-780-280

Mobile / WhatsApp +86 130 1601 3265

R&D center, Guangzhou +86 20 28185170

Plant in Xianning, Hubei · R&D in Guangzhou, Guangdong